The new road:
timetable for construction
The Watford Health Campus road is now under construction. Work on the road is expected to be completed by autumn 2016.
Below is the current timetable for when we expect work to start and finish across the various lengths of the road.
Date | Length of road under construction | Update |
---|---|---|
Jun 2015 to Aug 2016 | Wiggenhall Junction to Croxley Rail Link Bridge | Started |
Jul 2015 to May 2016 | Wiggenhall Road Works | Started |
Jul 2015 to Jul 2016 | Croxley Rail Link Bridge to Central Roundabout | Started |
Jul 2015 to Jul 2016 | Central Roundabout to Watford Hospital Roundabout | Started |
Jul 2015 to Nov 2016 | Dalton Way Junction | Started |
Aug 2015 to Jul 2016 | Croxley Rail Link Bridge and Culvert | Started |
Aug 2015 to Jul 2016 | Link Road through Oxhey Park | Started |
Sept 2015 to Dec 2015 | Watford Hospital Roundabout to Willow Lane | Started |
Latest update: 10 MARCH 2016
Wiggenhall Road:
Traffic management will be in place on this section of Wiggenhall Road until April 2016.
Off peak lane closures will take place from 12 May – 12 June 2016. Full road closures will take place from 8pm to 6am in March 2016 on the following dates:
- Saturday 12March
- Sunday 13 March
- Saturday 19 March
- Sunday 20 March
There will also be a lane closure on the following dates. This will be off peak – 9.30am – 4.30pm with two way traffic lights in operation so that vehicles can still drive into and out of Watford via Wiggenhall Road. The dates of the lane closure are:
- Tuesday 29 March – Friday 1April 2016
- Monday 4 April – Friday 8 April 2016
- Monday 11 April – Friday 15 April 2016
Full road closures will take place from 8pm to 6am from 21 June to 12 July 2016.